Bathroom Plan first draft
Page history
last edited
by peterga 13 years, 8 months ago
Calendar
- July 26 - Demo
- Pull out fixtures
- Drop ceiling
- Demo all wall surfaces
- Break up floor
- Remove plywood basement ceiling
- Start on chimney?
- July 26 - Call roofer (shoot for Wed afternoon)
- July 26 - Kemal back in town, order tile 7/27?
- July 27 - Complete chimney removal
- July 28 (if possible) Roofer
- July 27-30 - Large window arrives (will call at Windows, Doors & More in Ballard)
- July 28-29 - Complete plumbing, framing
- July 29 - All tile but pebble should arrive (1-2 days lead time)
- July 29 - Furnace install
- July 30 - Install windows, Electric, HVAC
- July 31 - Aug 6 - Dry wall & Tile
- Aug 7 - Aug 13 - Finishing